COLORBOND METAL ROOF REPLACEMENT SUCCESS STORY

Defying Downpours: Overcoming Rainy Days
SPEAK TO AN EXPERT
Scroll for more
CLIENT PROFILE

Client: Henrietta Street Trust

Sector: Class 5 Office Building

Location: Chippendale, Sydney

Project Value: $200,000

Background: During heavy rains, the tenants were faced with uncontrollable leaks and instances of ceiling collapse caused by a deteriorating metal roof and rusted box gutter.

A Ticking time bomb

Water ingress, once detected, should never be underestimated, as it has the potential to escalate into a much larger and more expensive problem.

Mould Infestation Health Risk

Compromised Structural Integrity

Increased Financial Repair Costs

OUR QUALITY GUARANTEE

Adhering to Australian Standards for roof replacement  was non-negotiable.

We approached the task with a commitment to quality, ensuring that every aspect of the repair work met these rigorous standards.

To provide the Owners with peace of mind and underscore our confidence in our work, we offered a substantial 10-year guarantee.

Adherance to Australian Standards 1562.1 Installation of Metal Sheet Roof and Wall Cladding

Adherance to AS 3500: Plumbing and Draiange

Workmanship and Materials Guarantee

Minimise downtime and protect the exposed roof

To mitigate weather-related risk, we adopted a staged approach

With forecasted wet weather, the project demanded swift execution

OUR OBJECTIVE

In the face of unforgiving rains,  we were faced with 2 options;

‍1) Let the ceiling collapse or
2) Work admist the rain with a robust strategy

Our  objectives were: stop water ingress and safe guard the buildings interior from moisture.

Box Gutter & Sump Upgrades

Purlins & Roof Clean

Sarking & Roof Sheeting

Capping & Flashings

Spray Testing

Construction METHODOLOGY

Our construction methodology followed a staged approach where by at the end of each day, we reinstated the old roof sheets to mitigate weather-related risks.

During the course of the project, our superintendent conducted regular quality assessments to verify the effectiveness of our workmanship, ensuring that the application was compliant and leak-free.

1. Box Gutter Upgrades

Installation of Box Gutter SupportsReplace severely deteriorated and moisture-damaged sleepers with like-for-like.

Increase Box Gutter CapacityInstall new Colorbond 270mm (w) x 100mm (h) with built-in 1:100 falls to allow free-flowing water during heavy rain events

Install New Sumps with Mesh Guards:Install new 600mm (l) x 270mm (w) x 200mm (d) sumps with mesh basket leaf guards to slow down water flow into downpipes to prevent back-charging into internal areas

2. Purlins & ROOF CLEAn

Clean Roof Cavity:Remove and dispose of existing roof insulation and vacuum clean the roof cavity to make way for new isulation.

Installation of new purlins:Replace all existing purlins with new Lysaght Zinalume Purlins at 800mm c/c to guarantee falls to  roof sheets and to allow larger box-gutters

3. Sarking and  METAL sheeting

Install new Sarking & Insulation: Install new vapour permeable sarking and  insulation batts to decrease heating and cooling costs

Install new Drainage Battens:Start Install new drainage battens to between sarking and roof sheeting to facilitate air and moisture flow.

Install New Metal Roof Sheeting:Apply caulk at corners and edges where tiles meet other materials or fixtures to ensure a watertight seal. Install any trims to protect tile edges to create a clean transition to adjacent surfaces.

4. cappings and DETAILING

Install new step flashings to adjoining building: Rake out existing brick joint and recess install our flashing into the building. Install polyurethane to seal.

Install Perimeter Cappings:Double seal install all cappings beneath and over laps to ensure zero moisture penetration. Our cappings were installed with a double drip-groove to eliminate any chance of capillary action.

Detail Roof Penetrations:We had 3 types of roof penetrations: AC Services
Threaded Rods, Vents.
1) AC Conduits were detailed by pulling the cables through a supported 1-way PVC pipe
2) Threaded rods were embeded in epoxy and oversealed
3) Vents were detailed with dektites, hose-clamps and top-sealed with Sikaflex Pro.  

PROJECT OUTCOME

Compliance: AS1562.1: Metal Roofing & Cladding

Structural Integrity: Extended lifespan

Reduced Premiums: Reduced Insurance Risk

Peace of Mind: Workmanship Guarantee

SPEAK TO AN EXPERT

OUR THOUGHTS

Metal Roof Replacement is a skill. Like every other skill, there are amateurs then there are the professionals. The results you achieve depend on the team you choose and the culture they have.

Our team are experts in their craft, they know the difference between a good and great product, they are the first to identify intricate details, utilise new technologies and strategies whenever they appear.

ATOMIC PROJECTS is the ultimate all-in-one building partner guiding you from the first to last day.

There is no one better on the planet to bring your project to life.

TWO ROADS AHEAD

Over the last 4 years we have worked exceptionally hard in delivering projects all over Sydney.

We have access to over 1,500 people Sydney-wide, with specialists, experts and professionals in every field imaginable.

All dedicated to the pursuit of excellence.

After learning all of this, you have two possible outcomes.

1

Keep looking, and hire an amateur

2

Act now, and hire a professional

WHICH VERSION WILL YOU PURSUE?
START NOW
REMEDIAL & FIT OUT

THE ULTIMATE GUIDE

your UNFAIR advantage